Project Planner Tab
The Project Planner tab in the Project Planner ribbon contains the following commands.
Project Planner
Refresh updates the Project Planner hierarchy,
if necessary. For example, if multiple users are accessing the
same plan simultaneously, this will update the plan to reflect
any changes made by other users.
Create Project Plan
opens the Create
Project Plan window so you can start again from a blank plan,
or import an existing plan from another project.
Delete Entire Plan deletes every
gate and removes every action from the plan.
Item
Properties allows you to view or edit the Identifiers
defined for the current plan. These identifiers can be used in
the Analysis Explorer to explore
all of the different types of analyses (including project plans)
in the current database.
Clipboard
Paste pastes
the contents of the Clipboard into the level below the selected
gate (or on the same level of the selected action). If you want
to paste gates only (without sub-gates and actions), use the Paste
Without Actions command.
Cut cuts the selected gate/action and any dependents
to the Clipboard. You can paste this information into another
Project Planner within the same database.
Copy copies the selected gate/action and any
dependents to the Clipboard. To copy everything, use the Copy Entire Plan command. You
can paste this information into another Project Planner within
the same database.
Delete deletes the selected gate/action and
any dependents.
Gate
Add Gate
- Add Same Level Gate adds a gate on the same level as the selected gate.
- Add Next Level Gate adds a gate one level below the selected gate.
- Add Gate adds a top-level gate to the end of the plan.
- Insert Gate inserts a gate at the selected location.
- Add Action creates a new action resource.
- Reuse Action Resources allows you to select existing action(s) from the project that a) are not already used in the current plan and b) have dates that fit within the current gate. Specifically, the action’s start date can’t be before or more than a year after the gate’s start date. (See Select Resource window.)
- Reuse FMEA Actions allows you to select one or more XFMEA/RCM++ system hierarchy items from the current project that have FMEAs. You can then select to use existing action(s) from those particular FMEAs in the project plan.
- Dashboard Viewer opens the Dashboard Viewer so you can view dashboards based on predefined layouts.
- Dashboard Manager opens the Dashboard Layout Manager so you can create, edit and delete the predefined layouts that will be available for any user to view for any project plan in the database.
- Export View to Excel exports the entire hierarchy and all displayed columns to an Excel sheet in a format that's suitable for presentation.
- Import Hierarchy and Export Hierarchy use an Excel format that's suitable for recreating the plan hierarchy in another project plan using information about precedents, outline level, etc.
Use Precedence, when selected,
automatically sets a new gate's precedent to the prior gate,
which allows you to take advantage of
expected
timelines and ensure that there are no gaps between gates.
If you clear this option, the default precedent will be "None."
Edit Gate opens the
Gate
Properties window.
Promote and
Demote moves the selected gate to
the next higher or lower level in the plan. An item can be
demoted only if there is another item on the same level and
above the selected item that it can be demoted under.
Action
Add Action
Edit Action opens action
properties window. (See
Actions
in the Project Planner.)
Tools
Remove Gaps in Dates
automatically assigns precedents to every applicable gate.
This ensures that there will be no gaps in the planned
or expected timelines, and it allows the expected dates
for an activity to automatically shift in response to
delays in prior activities. (See
Project
Planner Timelines.) You can choose to remove gaps
in the Entire Plan
or just for the gates that fall under the selected
Branch.
Check Utilization opens
the Check Utilization
window so you can examine the utilizations for individual
users and facilities across multiple actions (e.g., is
a particular user assigned to too many actions at the
same time, or is a particular test facility already booked
for a particular timeframe).
Expand All and
Collapse
All expands or collapses the gates in the project
plan hierarchy.
Dashboard
Excel Import/Export
Copy
Current View copies the currently visible
contents of the plan hierarchy or
Gantt
chart to the Clipboard as a graphic that can
be pasted to other applications.