Project Planner Tab
The Project Planner tab in the Project Planner ribbon contains the following commands.
Project Planner
 
		   Refresh updates the Project Planner hierarchy, 
		 if necessary. For example, if multiple users are accessing the 
		 same plan simultaneously, this will update the plan to reflect 
		 any changes made by other users.
                                                    
 
		   Create Project Plan 
		 opens the Create 
		 Project Plan window so you can start again from a blank plan, 
		 or import an existing plan from another project.
   Delete Entire Plan deletes every 
		 gate and removes every action from the plan.
   Item 
		 Properties allows you to view or edit the Identifiers 
		 defined for the current plan. These identifiers can be used in 
		 the Analysis Explorer to explore 
		 all of the different types of analyses (including project plans) 
		 in the current database.
Clipboard
                                                    
 
		   Paste pastes 
		 the contents of the Clipboard into the level below the selected 
		 gate (or on the same level of the selected action). If you want 
		 to paste gates only (without sub-gates and actions), use the Paste 
		 Without Actions command.
 
		   Cut cuts the selected gate/action and any dependents 
		 to the Clipboard. You can paste this information into another 
		 Project Planner within the same database.
 
		   Copy copies the selected gate/action and any 
		 dependents to the Clipboard. To copy everything, use the Copy Entire Plan command. You 
		 can paste this information into another Project Planner within 
		 the same database.
 
		   Delete deletes the selected gate/action and 
		 any dependents.
Gate
                                                    
 
		   Add Gate
- Add Same Level Gate adds a gate on the same level as the selected gate.
 - Add Next Level Gate adds a gate one level below the selected gate.
 - Add Gate adds a top-level gate to the end of the plan.
 - Insert Gate inserts a gate at the selected location.
 - Add Action creates a new action resource.
 - Reuse Action Resources allows you to select existing action(s) from the project that a) are not already used in the current plan and b) have dates that fit within the current gate. Specifically, the action’s start date can’t be before or more than a year after the gate’s start date. (See Select Resource window.)
 - Reuse FMEA Actions allows you to select one or more XFMEA/RCM++ system hierarchy items from the current project that have FMEAs. You can then select to use existing action(s) from those particular FMEAs in the project plan.
 - Dashboard Viewer opens the Dashboard Viewer so you can view dashboards based on predefined layouts.
 - Dashboard Manager opens the Dashboard Layout Manager so you can create, edit and delete the predefined layouts that will be available for any user to view for any project plan in the database.
 - Export View to Excel exports the entire hierarchy and all displayed columns to an Excel sheet in a format that's suitable for presentation.
 - Import Hierarchy and Export Hierarchy use an Excel format that's suitable for recreating the plan hierarchy in another project plan using information about precedents, outline level, etc.
 
   Use Precedence, when selected, 
			 automatically sets a new gate's precedent to the prior gate, 
			 which allows you to take advantage of 
			expected 
			 timelines and ensure that there are no gaps between gates. 
			 If you clear this option, the default precedent will be "None."
   Edit Gate opens the 
			Gate 
			 Properties window.
   Promote and 
			
 Demote moves the selected gate to 
			 the next higher or lower level in the plan. An item can be 
			 demoted only if there is another item on the same level and 
			 above the selected item that it can be demoted under.
Action
                                                        
   Add Action
   Edit Action opens action 
				 properties window. (See 
				Actions 
				 in the Project Planner.)
Tools
   Remove Gaps in Dates 
				 automatically assigns precedents to every applicable gate. 
				 This ensures that there will be no gaps in the planned 
				 or expected timelines, and it allows the expected dates 
				 for an activity to automatically shift in response to 
				 delays in prior activities. (See 
				Project 
				 Planner Timelines.) You can choose to remove gaps 
				 in the Entire Plan 
				 or just for the gates that fall under the selected 
				Branch.
                                                            
   Check Utilization opens 
				 the Check Utilization 
				 window so you can examine the utilizations for individual 
				 users and facilities across multiple actions (e.g., is 
				 a particular user assigned to too many actions at the 
				 same time, or is a particular test facility already booked 
				 for a particular timeframe).
   Expand All and 
				
 Collapse 
				 All expands or collapses the gates in the project 
				 plan hierarchy.
                                                            
   Dashboard
                                                                
   Excel Import/Export
                                                                    
 
						   Copy 
						 Current View copies the currently visible 
						 contents of the plan hierarchy or 
						Gantt 
						 chart to the Clipboard as a graphic that can 
						 be pasted to other applications.